PROJECT AUTHORIZATION PACKET ID: PMT-ALHR
CONTRACT ID EMARS PROGRAM CODE AUTHORIZATION NO:
1358001D      13580 1
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized.
PROJECT ID PROJECT ID NUMBER FEDERAL PROJECT NUMBER 6 YR PLAN ITEM NUMBER 6 YR PLAN ITEM PARENT NUMBER


STP 9031010

01-08952 1-.-
PROJECT TYPE PROJECT LENGTH NUMBER OF BRIDGES SYSTEMS
NOT APPLICABLE 0.6900 MI
PROJECT PHASE
&
RESPONSIBILITY
PLANNING DESIGN RIGHT OF WAY UTILITIES
CONSTRUCTION TITLE DEEDED TO: MAINTENANCE OTHER
FUNDING & TIME
ACCOUNTABILITY
PARTICIPATING AGENCIES
FEDERAL STATE DOH LOCAL OTHER
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER PHASE FUND PROGRAM FEDERAL FISCAL YEAR STATE FISCAL YEAR
FEDERAL APPR
CODE
CURRENT FUNDING REQUEST
1-8952 D 1100 FD04 2023 $1,250,000.00
CURRENT FUNDING REQUEST TOTAL: $1,250,000.00
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES
PHASE TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST)
PLANNING $0.00
DESIGN $1,670,000.00
UTILITIES $0.00
R/W $0.00
CONSTRUCTION $0.00
NON-HIGHWAYS $0.00
  Total: $1,670,000.00
REMARKS: THIS MODIFICATION PROVIDES ADDITIONAL STATE (FD04) DESIGN FUNDS FOR FINAL DESIGN. (FHWA APPROVED DESIGN FUNDING FOR FUTURE FEDERAL MATCH ON OTHER PHASES)
 
Project Approval Recommended By:
James Ballinger   10/9/2022
Signed and Approved by:
Jim Gray   10/10/2022
AUTHORIZATION LOCATION
ITEM NO. COUNTY DIST FACILITY NAME
ROUTE LENGTH SCOPE
01-08952.00 CALLOWAY


1 COLDWATER RD KY 748 0.6900 MI IMPROVE N 16TH STREET FROM KY 1327 (5 POINTS) TO KY 121 (2020CCN)